How to: See the Expected Finish Date of an Agility project

This feature is available in all editions

Question

Is there any way to see a graph showing the Expected Finish Date for an entire project? Assuming I have assigned all my stories, I was expecting the burndown graph to show something like that, (like Velocity shows Planned Velocity for future iterations/sprints) but the burndown line ends on the current sprint, no matter which view I choose.

Answer

Burndown charts show actual burndown up through the current period. The feature-level burndown chart is driven by the completion of features themselves and does not have any direct relationship to the sprint schedule. When a feature is complete, it triggers a change in the burndown chart regardless of the sprint's status or timing.

You can use the Release Forecasting Report to show a projected completion date and number of sprints. You can input the remaining estimate and velocity directly or have the system calculate it based on parameters you select.

 

Was this article helpful?
0 out of 0 found this helpful

Comments

0 comments

Please sign in to leave a comment.