This feature is available in all editions
Question
I want to track the progress of a story/backlog item in the grid. Please explain what data is used in the calculation?
Answer
The indicators on the progress bar are calculated from the Effort logged on a work item. The calculation for the Done amount in the progress bar changes when you turn on Effort Tracking, as follows:
- When Effort Tracking is enabled, the progress bar uses the actual Done amount (= sum of Effort) for the sprint
- With Effort Tracking not enabled, the calculation estimates the Done amount as (Detail Estimate - To Do)
To learn more about progress bars, see Release Scheduling Progress Bars for more information.