Question
I would like to edit the Detail Estimate or To Do estimate for Tests that are children of portfolio items. How can this be done?
Answer
Portfolio items don't get added to sprints/iterations for tracking, so their tests don't have tracking numbers on them (Detail Estimate or To Do). The tests at this level are meant to be checklist-type items to help detail the scenarios that the feature is intended to cover. To actually plan and track time on verification activities, you can create a schedule-able story or test set to plan and track specific testing efforts.