Question
Our project tree contains three sub/child projects below the All Projects (System). When I try to add a sprint/iteration to the lowest-level project, the sprints are also added to the other child projects as well. How do I add a sprint/iteration to just that one sub/child project?
Answer
This can occur if all three child projects use the same sprint schedule.
You can assign a unique sprint schedule for any project within the project tree. The project schedule setting can be changed under certain conditions and will un-assign any open items scheduled in a sprint/iteration. You can make this change by editing the Sprint Schedule assigned to the project in the Project details.
Important
Editing and removing a project's sprint schedule requires the following:
- You must have sufficient Project Administration rights to access the project
- The project cannot have any closed backlog items, defects, or portfolio items scheduled in a sprint/iteration. To verify this, check the following page.
- Product Planning > Backlog
- The project cannot have any closed retrospectives in the sprints being changed.