This feature is available in all editions
Overview
The best way to see the progress of a sprint/iteration is on the Sprint/Iteration Dashboard report. The Sprint Dashboard report shows a set of graphs specific to a sprint, complete with a work burndown, work and scope trends, acceptance test progress, and member load information.
Additional Options
You can also see sprint progress here:
- Burndown Report
The Burndown report is the cornerstone of sprint progress reporting and displays a trend of the completed (if tracked) and remaining work for the team within a sprint/iteration. The trend line should move from the upper left to the lower right of the graph. A slope that hits zero by the end of a sprint/iteration indicates the team is on track to complete everything on time. - Sprint Summary Section of the My Work Page
Quick status views of a sprint are also visible in the progress bars displayed the in Sprint Summary section of the My Work page. Sprint progress bars provide a quick status, showing both the around of work completed vs. remaining and the current timeline within a sprint/iteration.
Comments
Please sign in to leave a comment.